What are the City's average permit turnaround times?

Permit turnaround times will vary depending on how complex a project is, how many corrections of plans are needed, and how quickly and completely responses are submitted back to the City when corrections are needed.  Following are average time frames for the listed permit types:


  • Building permits for new single-family residential homes:  initial review comments in 2 - 4 weeks
  • Building permits for new commercial buildings:  initial review comments in 4 - 6 weeks
  • Civil permits (Fill & Grade) for commercial projects:  initial review comments within 4 weeks
  • Planning Permits for Administratively Approved projects: initial review comments in 4 - 6 weeks 
  • Planning Permits for projects requiring Hearing Examiner recommendations or approvals:  initial review comments in 6 - 8 weeks


Show All Answers

1. What incentives are there for businesses in Mount Vernon?
2. What is the population of Mount Vernon and Skagit County?
3. What are the City's average permit turnaround times?
4. How do I get a business license?