2019 Sanitary and Storm Sewer Lining

Project Description:
This project includes lining approximately 4,454 feet of sanitary sewer pipe and approximately 895 feet of storm sewer pipe with a cured in place pipe (CIPP) liner system. Work also includes grouting and restoring laterals, trimming intruding laterals, and lining pipe under a railroad.

Funding:
Utility Funded

Project Status:
Three bids were received for this project ranging from $699,406.77 - $866,120.94. The City awarded this project to Insituform Technologies of Chesterfield, MO on August 14, 2019.  This project is expected to be complete by December 31, 2019.. 