Bid Award: May 23, 2018 - $1,487,586.00
Contractor: SRV Construction, Anacortes, WA
Construction Management: City of Mount Vernon
Project Engineer: Darin Christen, PE, Senior Engineer
Contact Information: (360) 336-6204
Funding: Transportation Benefit District
Sign up here for Construction and Road Closure Notifications
Project Description:
This project included road improvements on S 2nd St (Kincaid - Blackburn); Section St (Laventure Rd - S 18th St); Section St (S 18th St west - Denny St); Laventure Rd (Section to Fowler); Warren St (N 6th - Dead End east of N 11th St)
Current Status:
The project was completed on March 4, 2019, in the amount of $1,634,588.38.