2019 Sanitary and Storm Sewer Lining

Project Description:
This project includes lining approximately 4,454 feet of sanitary sewer pipe and approximately 895 feet of storm sewer pipe with a cured in place pipe (CIPP) liner system. Work also includes grouting and restoring laterals, trimming intruding laterals, and lining pipe under a railroad.

Funding:
Utility Funded

Project Information:
Three bids were received for this project ranging from $699,406.77 - $866,120.94. The City awarded this project to Insituform Technologies of Chesterfield, MO on August 14, 2019.

Project Update (10/18/2019):
The contractor will be on Roosevelt on Oct. 19th working on the bypass under the railroad tracks. They will return on Oct. 23rd & 24th on Manito, Oct. 25th on Kulshan, and return on Oct. 26th to Roosevelt.

This project is expected to be complete by December 31, 2019.

If odors are observed, try running water down drains that may not be used regularly. 