19th Street Culvert Rehabilitation

Bid Award: August 12, 2020 - $139,512.10 (Small Works Project)
Contractor: Oceanside Construction of Bellingham, WA
Construction Management: PBS Engineering & Environmental of Issaquah
Project Engineer: Bill Bullock, City Engineer
Contact Information: (360) 336-6204
Funding: Surface Water Utility

Sign up here for Construction and Road Closure Notifications

Project Description:
This project includes the replacement of 140 feet of existing 30-inch culvert with an 8-foot open channel. The banks will be temporarily stabilized with rock.

Current Status:

The project is currently under construction and is anticipated to be complete in mid October 2020.